Is this really a towpath improvement ?


Featured Posts

Classic outsourced sub contracted works unsupervised when being undertaken with no formal inspection/hand back procedures . Cape locks classic dreadful lock gate replacement last year no excuse for no supervisor it's just round the bend from the CRT Hatton base .Never saw any CRT on site as I passed daily . No improvement to the locks either.....

Link to comment
Share on other sites

  • 2 months later...
On 28/05/2023 at 21:05, Richard T said:

There are some positives about the scheme - there are new bollards the Leicester side of the chain bridge which will save the need for moorers to use pins. There is still a grass bank along the stretch used for mooring.

 

I always like to keep an eye on CRT management (or lack of) on projects such as this, dredging, gate repairs etc.

So today, I had a local visit and took half an hour to enjoy the CRT new gravel topped towpath with new bollards.

Chain bridge end....smooth transition enabled from Chain Bridge end.

20230825_104147.jpg.eaf1ecebb3a9aa7d5a4e9b655a324aad.jpg

 

I believe someone has forgotten the gravel top...20230825_104210.jpg.72de96358b8efe98edbbc99bd8738cc2.jpg

 

Lots of new ( bollard).....holes, some obvious, some ankle breakingly hidden...

20230825_105746.jpg.ed0160c787156ad5fccb650c1cea6a94.jpg

20230825_104235.jpg.32050420fbe09d6f9793327c020555c6.jpg20230825_104300.jpg.c2464815db44aed218f44a1b2f832eaf.jpg

 

 

20230825_104319.jpg.d7f75b3acaeafe3265ed6a6dd72533b9.jpg

 

So, make your mind up time, high speed cycle way or....community asset

 

20230825_105724.jpg

Edited by matty40s
Link to comment
Share on other sites

4 hours ago, MtB said:

I'm surprised there are never any signs saying "DANGER, DEEP WATER"

 

But then on thinking about it, maybe there isn't any. 

 

 

Or DANGER SHALLOW WATER. But they would have to order and erect thousands of signs. 

Link to comment
Share on other sites

6 hours ago, Paul C said:

Matt, they put the signs up before they lay the gravel, so that they're there ready for when the gravel is, rather than having loose gravel but no signs (safety issue). But don't let it interfere with your criticisms of CRT......

The towpath was supposed to be completed at end of May, and then gravelled in midsummer when the tarmac was warm enough... not left smooth tarmac.

The gravelling has not been completed, neither have the bollards....which has left at least 12 holes which could break your ankle of getting off boat in the long grass.

Dont let this stop you criticising a post for the sake of criticising.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.