Bosley Locks closed again


Bugsworth Tippler

Featured Posts

https://canalrivertrust.org.uk/notice/14988/lock-1-to-lock-12-bosley-flight-macclesfield-canal

 

Notice Details
From Date:
10th April 2019 at 13:00
To Date:
until further notice
Type:
Navigation Closure
Reason:
Structure failure
Description:

Our teams, whilst operating lock 3 today, have discovered a large void in the lock wall quadrant on the off-side.

Unfortunately, we have had to take the decision to close the Bosley Flight while our teams plan a temporary solution to allow passage.

We hope to provide you with an update by tomorrow afternoon.

 

 

Location:
Macclesfield Canal
Starts At:
Lock 1
Ends At:
Lock 12
Link to comment
Share on other sites

3 hours ago, Sea Dog said:

Is that a thing then?  

The comment about the Bosley-Leek link was tongue in cheek as I can't see any major developments such as this happening any time soon. My recollection (which I'll investigate further) is that the proposal involved using the feeder channel above Bosley lock 1 to allow boats to access Rudyard lake and then on to Leek. The worry was that the Harecastle tunnel might become un-navigable and uneconomic to repair so this alternative means of movement north to south was considered. I think there were some preliminary plans for the Leek end but, of course, nothing ever happened. I'm sure someone with a better memory or more knowledge can correct me or add to this.

Link to comment
Share on other sites

30 minutes ago, Bugsworth Tippler said:

the proposal involved using the feeder channel above Bosley lock 1 to allow boats to access Rudyard lake and then on to Leek

Sounds unlikely - the feeder channel connects to Bosley reservoir, not Rudyard, which is on the other side of the Dane.

 

 

Link to comment
Share on other sites

38 minutes ago, Señor Chris said:

Sounds unlikely - the feeder channel connects to Bosley reservoir, not Rudyard, which is on the other side of the Dane.

 

 

Leek-Bosley.jpg.08349cad241b80490992409df71c3019.jpg

 

The above was found on an old Macclesfield Canal Society page. https://ipfs.io/ipfs/QmXoypizjW3WknFiJnKLwHCnL72vedxjQkDDP1mXWo6uco/wiki/Macclesfield_Canal.html

 

There is another archived article I can't access on the same subject and I definitely remember seeing plans for changes at the end of the Caldon Canal (Leek branch).

Link to comment
Share on other sites

19 hours ago, Bugsworth Tippler said:

Leek-Bosley.jpg.08349cad241b80490992409df71c3019.jpg

 

The above was found on an old Macclesfield Canal Society page. https://ipfs.io/ipfs/QmXoypizjW3WknFiJnKLwHCnL72vedxjQkDDP1mXWo6uco/wiki/Macclesfield_Canal.html

 

There is another archived article I can't access on the same subject and I definitely remember seeing plans for changes at the end of the Caldon Canal (Leek branch).

If harecastle becomes unnavigable from subsidence wouldn't it be easier to dig it deeper and put a stop lock either end?

Link to comment
Share on other sites

From Date:
10th April 2019 at 13:00
To Date:
11th April 2019 at 12:00 inclusive
Type:
Navigation Closure
Reason:
Structure failure
Notice updates:
11/04/2019 @ 13:35

The Flight is now open for navigation

Our Teams have managed to erect a temporary platform which has been built above the void to enable the lock to still be in use.

Description:

Our teams, whilst operating lock 3 today, have discovered a large void in the lock wall quadrant on the off-side.

Unfortunately, we have had to take the decision to close the Bosley Flight while our teams plan a temporary solution to allow passage.

We hope to provide you with an update by tomorrow afternoon.

 

Link to comment
Share on other sites

Notice Alert

Macclesfield Canal
Starts At: Lock 1
Ends At: Lock 12

Wednesday 17 April 2019 08:00 until Wednesday 17 April 2019 17:00

Type: Navigation Closure
Reason: Structure failure


 

Update on 16/04/2019:

 

Our teams will be dismantling the temporary platform and will be carrying out a permanent repair to the quadrant at Lock 3.

Whilst these works are being carried out the Bosley Flight will be closed for 1 day and will re-open for navigation on the evening of Wednesday 17th April.

 

Update on 11/04/2019:

 

The Flight is now open for navigation

Our Teams have managed to erect a temporary platform which has been built above the void to enable the lock to still be in use.

 

Original message:

 

Our teams, whilst operating lock 3 today, have discovered a large void in the lock wall quadrant on the off-side.

Unfortunately, we have had to take the decision to close the Bosley Flight while our teams plan a temporary solution to allow passage.

We hope to provide you with an update by tomorrow afternoon.

 

 

You can view this notice and its map online here:
https://canalrivertrust.org.uk/notice/14988/lock-1-to-lock-12-bosley-flight-macclesfield-canal

You can find all notices at the url below:
https://canalrivertrust.org.uk/notices

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.