Update as of last nite -
100 tons of clay has now been deposited between Middle Bridge and my boat with a further 60 tons coming today -
Pumps should be put in over the weekend and tested etc with a view to start pumping on Monday (120 gallons a second i am told)
3rd boat (Odyssey) broken into and burgled last week -
BW workers renewing sandbags and drinking tea etc - water delivered to other boat (The Meggy) various BW project managers and "asset" engineer wandering about - NO personal contact from BW to the boats at all - NO backup from the Police - security people on site today as far as the plant equipment is concerned and plenty of fretting over the stranded fish - the situation with the 3 stranded boaters sucks almost as much as the mud that we are marooned in - on the bright side much blacking has been carried out - the owners of the Meggy who do not know the area and are devoid of transport enquired to BW about Blacking and were told that BW would sell them some for 25 quid ! - you think that somebody from customer care would have knocked on the boats concerned and offered them some free blacking to be going on with -
They would'nt give you the steam off a turd !